| New Head Office, Gateway House,
Styal Road, Styal

Amplivox + Ultratone have been at the forefront of audiological
technology for the last 60 years, undertaking the design, manufacture
and distribution of hearing aids and equipment to hospitals and
the general public through a national chain of hearing aid consulting
centres.
With continued growth and success,
it became apparent that the facilities available at the head office
and training centre in Wilmslow, Cheshire, would soon reach saturation.
So in 2004 the company acquired a new 2,310m2 Head Office building
some 3 miles away in Styal, Cheshire.
The new open-plan building consisting
of separate three and four storey blocks with an interlinking services
block would provided Amplivox + Ultratone with a blank canvas on
which to design a layout that would take them into the 21st Century.
Central to the refurbishment was the
installation of air conditioning throughout the building to create
an environment to maximise staff comfort throughout the year.

In July 2004 T. Jolly (Services) Ltd. were approached by an existing
customer, Certainty Group FM Ltd., to provide feasibility proposals
and prices for the installation of an air conditioning system to
serve the new head office of Amplivox + Ultratone Ltd.
The design criterion would have to meet strict
limitations set down by the client in terms of installation and
life-cycle costs, space availability and project duration. In addition,
the client wished to avoid making any aesthetic or structural changes
to the building, thus ruling out the installation of exposed ductwork
or pipework and preventing the construction of an external chiller
compound.
Furthermore, the computer server rooms and
IT areas would require separate controllers enabling room conditions
to be adjusted independently of surrounding areas.

Following discussions with the client to establish their needs and
a number of site surveys to determine the system limitations, T.
Jolly’s came up with a design incorporating four separate
variable refrigerant volume (VRV) air conditioning systems from
Daikin. Each system serving a single floor of both blocks with interconnecting
pipework running from roof mounted inverter driven heat pumps, down
the internal risers to the required ceiling level.
The critical IT areas were separated from
the relevant VRV system serving the rest of the floor and fed via
independent split systems, enabling them to call for cooling whilst
the surrounding offices served by the VRV can call for heating.
In addition, these split systems would remain operational should
the VRV systems need to be shut down for routine maintenance.
Before selecting equipment from Daikin, comparative products from
both Mitsubishi and Toshiba were considered, but the value, efficiency
and proven track record of the Daikin equipment allied to an excellent
technical support service and spare’s availability proved
compelling .
Work commenced on site in October 2004 with
the installation of pipework for the system serving the ground floor.
This was soon followed by the installation of the ceiling cassettes
and high-wall units, condensate drains and interconnection wiring.
The installation of the first, second and third floor systems then
followed, with the last of the fifty indoor units being installed
in late November 2004.
The first of the four inverter driven heat-pump
condensing units was lifted onto the roof by crane in early December
2004, in time for commissioning and handover to the client on schedule
and in time for the christening of the new building which was celebrated
with a Christmas party. For further information on this case study
or to enquire about air conditioning installations, please contact:
John-Taylor@tjolly.co.uk
|